ASSEMBLY

  • Standard system

    • Assembly of main elements (e.g. boxes)

    • Transfer of main elements to floor or ceiling slab

    • Completion of reinforcement to height of approx. 1.8 m

    • Transfer of remaining main elements

    • Assembly of platform decking and railings

    • Finalisation (hydraulics, lighting, safety nets, etc.)

  • Round formwork

    • Assembly of inner cylinder

    • Completion of reinforcement to height of approx. 1.8 m

    • Assembly of outer cylinder

    • Assembly of platform decking and railings

    • Finalisation (hydraulics, lighting, safety nets, etc.)