• Filling of the formwork at start of slipforming(approx. 4-6 hours)
  • Continuous raising of formwork (approx. 10 - 40 cm/hour) in 2 or 3 shifts
  • The slipforming rate is determined with the customer, taking into account the expected temperature conditions, crane capacity and laydown rate for concrete and reinforcement.
  • Removal of the formwork at top of the wall and allowing to stand for at least 12 hours