Fire protection wall Münster

 

Fire protection wall for Warenverteilzentrum Brillux in Münster

Build time:
3 weeks in 2008
Height: 29,85 m
Slipform area: 4.222 m²
Concrete poured: 593 m³
Slipforming speed: 4,90 m/day
Country: Germany

Client:
 Oevermann Hochbau GmbH., Münster

 

 


We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies). You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.