Stair core for energy from waste plant Münster
Build time: 5,0 weeks in 2004
Height: 70,00 m
Slipform area: 7.366 m²
Concrete poured: 1.300 m³
Slipforming speed: 4,10 m/day
Country: Germany
Client: Joing Venture: RMHKW Münster