Step core for compound feed factory Raiffeisen Ems-Vecht
Build time: 3 weeks in 2021
Height: 35,00 m
Slipform aera: 1.830 m²
Concrete poured: 260 m³
Slipforming speed: 5,80 m/day
Country: Germany
Client: Kewe Bauunternehmen GmbH & Co.KG
{gallery}referenzen/treppenturm/galerie-laar{/gallery}
8 pieces of technology shafts and stairwells for Siemens Healthineers